School Board Approves Change Order, Reducing Bus Garage Project Cost by $23,300

SHARE NOW

The Russell County Board of Education has approved a change order that will reduce the cost of the district’s new bus garage project by more than $23,000.

During Monday’s monthly meeting, board members approved a deduct change order involving Branscum Construction’s general trades contract for the new bus garage located behind Russell Springs Elementary School.

Superintendent Michael Ford explained that the savings resulted from relocating a bus lift from the old garage to the new facility. The work associated with the lift pit and concrete construction cost less than originally anticipated.

The change order reduces the project’s contract amount by $23,300.

The original general trades contract totaled approximately $1,635,851.00. With the approved deduction, the revised contract amount is approximately $1,612,551.00.

Ford said the unused funds will be returned to the project budget.